The rail gap adjuster is used to adjust the rail joint clearance.
The rail gap adjuster is used to adjust the rail joint clearance.Due to the influence of climate change, train operation and other factors, the rail gap often changes.In order to ensure the traffic safety, the public works Department has certain requirements for the rail joint clearance, so the rail must be connected in series.The rail gap adjuster has a large thrust force, which can be used to complete the rail crossing task of 50kg / m, 60kg / m, 75kg / m.
Maximum thrust | 250kN |
The maximum stroke of working cylinder | 145mm |
oil pressure | 43Mpa |
The displacement of the piston in each working cycle of the oil pump plunger | 1.7mm |
Maximum operating force of handle | 260N |
The maximum rail gap for each adjustment | 140mm |
Overall dimensions(L*W*H) | 850*300*290 mm |
Net weight | 55kg |